Home > News > Content
Artificial Turf Wall Installation Process
Nov 21, 2018

      Artificial turf can not only be used in kindergarten venues, football stadiums, green in the hotel, balcony greening, green engineering, wall decoration and other aspects of the application after another.

  Among these uses, among them, the wall installation construction process is the most challenging. There are two reasons. First, the construction takes a long time. The width of the lawn produced by lawn manufacturers is 4 × 25 meters and the volume of lawn 100 Square meters. However, an office area of 100 square meters, the conventional height of the wall 3,4 meters, and some even only one meter high, which requires engineers to cut large pieces of lawn into pieces; second, a roll Lawn weight is 200kg, this weight is very difficult to glue the lawn firmly fixed on the wall, to achieve the best state of artificial lawn bonding directly to the professional construction and installation of the master installation on it.

  Although the construction is difficult, the advantages of wall-mounted lawn is undeniable, giving customers the feeling of the immediate, innovative label arises spontaneously; employees in such a beautiful company to work pride, confidence doubled; the most important Is the service life of more than 10 years.

  1.Before installing artificial turf need to prepare the auxiliary tools: long, wallpaper knife, artificial turf special glue, brush, rubber hammer, skeleton, electric drill, nails and so on.

  2.Artificial turf construction before the connection process, the artificial or artificial grass to be adhered to the ground or wall clean, and keep the surface of the dry water, artificial turf construction connection process, you also need to select the ambient temperature above 5 ℃ is Artificial turf optimal construction; open the lawn for 24 hours, release the lawn tension, making lawn paving effect without wrinkles, more beautiful.

  3.first dragon skeleton fixed on the wall. Draw the dragon frame against the wall with a brush to draw a small circle where the nail needs to be nailed, drill a nail with a power drill at the small circle, and secure the keel to the wall.

  4.According to the height of the wall, cut the lawn with the wallpaper knife to the required size, nail the nail on the skeleton.

  5.artificial turf solidification during the specific construction process: artificial turf construction, the curing time is generally three days, the final test strength is generally ten days. During artificial turf construction curing should pay attention to artificial turf maintenance.

  The difference between artificial turf wall installation and other installation is that it needs the support of the dragon skeleton, which is also the most important part in the wall installation, so as to fix the artificial turf more firmly.

DSC03274-1主